Existing ESB Ballyvouskill 220/110 kV substation Located in the townland of Caherdowney Millstreet, Co. Cork

Granted 17 Aug 2020 (final grant issued 21 Sep 2020)

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email

Key facts

  • Planning application 20/5281 at Existing ESB Ballyvouskill 220/110 kV Substation Located In The Townland of Caherdowney Millstreet, Co. Cork: Proposed modifications to the previously permitted development.
  • It was received by Cork County Council on 23 Jun 2020.
  • Status: Granted 17 Aug 2020 (final grant issued 21 Sep 2020).

Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register

Planning applications in Co. Cork

Council register

The council's register shows: Granted on 17 Aug 2020.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Proposed modifications to the previously permitted development

Proposed modifications to the previously permitted development (planning ref: 18/06438 granted on 7th March 2019).The proposed modifications will comprise the additional construction of one (1) harmonic filter, one (1) HV circuit breaker (including CT and VT), one (1) MV disconnector and earth switch, two (2) cable sealing ends, three (3) additional lightning masts (approximately 25m high) and additional lamppost lightning. It further includes a retaining wall (approximately 2.5m high), asphalt (non-permeable) surfacing, additional permanent access road, additional fencing to match existing 2.6m high palisade, additional permanent access gate and all other ancillary site development works. The development will remain an extension to the existing substation and this extension will have an overall site area (within the planning application boundary) of 0.73ha. Access will continue to be provided via a L5226 and the R582.

Location
Co. Cork Map
Planning reference
20/5281

Numbers and dates

Project type
Planning record
Received
23 Jun 2020
Decision to grant
17 Aug 2020
Final grant
21 Sep 2020
Site start notified
25 Nov 2021

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work packages named so far

  • Roads and site development worksNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 20/5281.Search the register

How we know this

From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 25 Nov 2021Notice filed · Construction of a new Static Synchronous Compensator (STATCOM) BuildingView the site start
  2. Completion certificate recordedRecorded in Nov 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Co. Cork

Get alerts for Co. CorkFree. We email you when new applications appear.

Free email alerts

Get new Cork projects by email

New applications, decisions and site starts in Co. Cork. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options