Infrastructure · Co. Cork
Express Red Long Term Car Park, Cork Airport, Lehenaghmore
Granted 25 Aug 2021 (final grant issued 6 Oct 2021)
We no longer update this application, so we can't email you about it. Get new planning applications in Lehenaghmore by email
Key facts
- Planning application 2140328 at Express Red Long Term Car Park, Cork Airport, Lehenaghmore: New 10kV single-storey substation with a lean-to incorporating…
- It was received by Cork City Council on 1 Jul 2021.
- Status: Granted 25 Aug 2021 (final grant issued 6 Oct 2021).
Source: the Cork City Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Lehenaghmore · Planning applications in Co. Cork
Council register
The council's register shows: Granted on 25 Aug 2021.
Search the Cork City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
New 10kV single-storey substation with a lean-to incorporating…
Permission for development which will consist of the construction of a new 10kV single-storey substation with a lean-to incorporating a diesel tank bund; generator; fencing and gates; pedestrian barriers; new pedestrian crossing and traffic calming; road markings; and all site development and drainage works adjacent to the existing substation. The proposed development will require the removal of 63no. long-term car parking spaces.
- Location
- Lehenaghmore, Co. Cork Map
- Council
- Cork City Council
- Planning reference
- 2140328
Numbers and dates
- Project type
- Infrastructure
- Received
- 1 Jul 2021
- Decision to grant
- 25 Aug 2021
- Final grant
- 6 Oct 2021
- Site start notified
- 11 May 2022
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 2140328 on planning.corkcity.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Cork City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 11 May 2022Notice filed · The construction of a 10kV Single storey substationView the site start
- Completion certificate recordedRecorded in May 2022 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.