Infrastructure · Co. Cork
Barnahely Ringaskiddy Co. Cork
Granted 5 Aug 2022 (final grant issued 20 Sep 2022)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 22/4629 at Barnahely Ringaskiddy Co. Cork: Two storey value added seafood factory building with R&D…
- It was received by Cork County Council on 23 Mar 2022.
- Status: Granted 5 Aug 2022 (final grant issued 20 Sep 2022).
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 5 Aug 2022.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Two storey value added seafood factory building with R&D…
The construction of a two storey value added seafood factory building with R&D and ancillary office accommodation to the first floor, complete with the following (i) signage (ii) car, cycle and motorcycle parking; (iii) internal access roadways, yard area with dock levellers, w.c. and shower facilities, back-up generators, and bunded fuel tanks (iv) fire water storage tank and associated pumps; (v) substation; (vi) security gates and fencing (vii) 1 no. access to the estate road; (viii) underground storm water attenuation, and all associated site development and landscaping works.
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 22/4629
Numbers and dates
- Project type
- Infrastructure
- Received
- 23 Mar 2022
- Decision to grant
- 5 Aug 2022
- Final grant
- 20 Sep 2022
- Site start notified
- 24 Apr 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 22/4629.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 24 Apr 2023Notice filed · the construction of a two storey fish processing factory building and associated worksView the site start
- Completion certificate recordedRecorded in Apr 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.