Infrastructure · Co. Cork
Wastewater Treatment Plant (WwTP) Macroom Sleveen East Co. Cork
Granted 30 Mar 2023 (final grant issued 2 May 2023)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 22/4630 at Wastewater Treatment Plant (WwTP) Macroom Sleveen East Co. Cork: Upgrade works.
- It was received by Cork County Council on 23 Mar 2022.
- Status: Granted 30 Mar 2023 (final grant issued 2 May 2023).
- Work was due to start on 14 Feb 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 30 Mar 2023.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Upgrade works
Upgrade works at the wastewater treatment plant which will consist of 1. Construction of a new storm overflow and flow splitting chamber, inlet works including grit removal system and full flow to treatment pumping station, 2 no. new integrated fixed-film activated sludge reactor tanks (Aeration Tanks), 2 no. final settlement tanks, final water sampling manhole while retaining the existing outfall to the River Sullane, return and waste activated sludge pumping stations, chemical building including lime and ferric sulphate dosing systems with bunded chemical storage tanks, 1no. storm water storage tank equipped with storm water pumps, 1 no. sludge picket fence thickener, odour control system, a sheet pile flood protection wall within the site boundary, boundary treatments include a weld mesh security fence, new internal access road and public lighting. 2. Construction of a new control and administration building. 3.Decommissioning of the existing wastewater treatment plant, equipment and associated structures as part of the upgrade works. 4. Construction of a 42 kWp photovoltaic (PV) solar panels on ground mounted frames on the north western area of the site. The PV panel shall be used to supplement the energy demands of the proposed WwTP and will be arranged with a panel area of 185 m² approximately. 5. Establishment of a designated area to be utilized by Cork County Council Roads Department and construction of a new entrance point. 6. All associated site development works above and below ground. A Natura Impact Statement (NIS) will be submitted to the planning authority with the application.
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 22/4630
Numbers and dates
- Floor area
- 185 m²
- Project type
- Infrastructure
- Received
- 23 Mar 2022
- Decision to grant
- 30 Mar 2023
- Final grant
- 2 May 2023
- Site start notified
- 14 Feb 2024
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 22/4630.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 14 Feb 2024Notice filed · phase 1 · Construction of a control building at Macroom waste water treatment plant, Co. Cork.View the site start
- 21 May 2024Notice filed · phase 2 · Construction of a Lime Dosing Building at Macroom WWTP, CorkView the site start
- 13 Aug 2024Notice filed · phase 3 · Construction of an ESB building at Macroom.View the site start
- 20 Aug 2024Notice filed · phase 4 · Construction of a MCC building at Macroom waste water treatment plant, Co. Cork.View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.