Site start · Co. Cork
Cork, Cork
Site start 29 Sep 2023
Key facts
- Site start record ABP-312076-21 at Co. Cork: 50 homes.
- The planning authority is Cork City Council.
- Status: Site start 29 Sep 2023.
Source: the Cork City Council planning register, as last seen on 12 Jul 2026. Search the council's register
Archived record
This application has left our current planning lists, so this page is no longer updated. We last saw it in the council's register on 12 Jul 2026. The details below are as they were then. The council's register has the current status.
What and where
50 homes
Construction of 50 no. new dwelling houses and associated site works, nos. 225 to 274 inclusive arderrow, ballyhooly road, ballyvolane, cork.
- Location
- Co. Cork Map
- Council
- Cork City Council
- Planning reference
- ABP-312076-21
- Application type
- Commencement Notice
- Owner named on the notice
- O Flynn Construction
- Agent named on the notice
- O Flynn Construction
Numbers and dates
- Homes
- 50
- Floor area
- 4,704 m²
- Estimated construction value
- €7.1m to €9.1mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Large residential
- Site start
- 29 Sep 2023
Documents and evidence
Check the record
- Council planning registerSearch planning.corkcity.ie for reference ABP-312076-21.Search the register
How we know this
From the Cork City Council planning register, as last seen on 12 Jul 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 29 Sep 2023Notice filed · phase 1 · Construction of 85 no. dwelling units and associated site works, nos 1-79 (incl.)...View the site start
- 22 Mar 2024Notice filed · phase 2 · Construction of 76 no. new dwelling houses and associated site works, nos. 80 to 144,214...View the site start
- 17 Sep 2025Notice filed · phase 3 · Construction of 34 no. duplex and apartment dwellings and associated site works...View the site start
- 19 Dec 2025Notice filed · phase 4 · Construction of 29 no. dwelling units, creche(shell only) and associated site works, nos...View the site start
- 18 May 2026Notice filed · phase 5 · Construction of 5 storey residential development to include 29 no. dwelling units...View the site start
- Completion certificate recordedRecorded in Sep 2023 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Sep 2023 · 5 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Sep 2023 · 5 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area