Infrastructure · Co. Sligo
Finisklin Business Park, Co Sligo.
Granted 30 Oct 2024
Key facts
- Planning application 2460293 at Finisklin Business Park, Co. Sligo: Development.
- The applicant is Abbott Ireland Diagnostics Ltd.
- It was received by Sligo County Council on 10 Sep 2024.
- Status: Granted 30 Oct 2024.
- Work started on site on 13 Jun 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Sligo County Council planning register, checked 2 Jun 2026. Open the council's file
Since you last looked
Worked out in this browser from the record's own dates. We do not send emails about it.
What and where
Development
development, located to the northeast of the existing facility, will consist of a new ESB substation and switch room to serve the existing facility. The substation measures 45.7 m² in plan area and 3.5m in height. The switchroom and a back up generator will be located on a raised gantry that will measure 121 m² and 7m in height and be situated 3.5m above ground level
- Location
- Finisklin Business Park, Co. Sligo Map
- Council
- Sligo County Council
- Planning reference
- 2460293
- Applicant
- Abbott Ireland Diagnostics Ltd
Numbers and dates
- Floor area
- 167 m²
- Project type
- Infrastructure
- Received
- 10 Sep 2024
- Granted
- 30 Oct 2024
- Site start
- 13 Jun 2025
Timeline
- Application received
- Granted
- Site start
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 2460293 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Sligo County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.
Site starts
Commencement notices for this permission
- 13 Jun 2025Work started · Development located to the north east of the existing facility consisting of the...
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area