  • Planning application 18600758 at Ballina Primary School, Ballina, Co. Tipperary: Single storey temporary prefabricated building.
  • It was received by Tipperary County Council on 14 Jun 2018.
  • Status: Granted 7 Aug 2018 (final grant issued 11 Sep 2018).
  • Work was due to start on 23 Oct 2018, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Tipperary County Council planning register, as last seen on 2 Jun 2026. Open the council's file

More planning applications in Ballina · Planning applications in Co. Tipperary

Council register

The council's register shows: Granted on 7 Aug 2018.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Single storey temporary prefabricated building

a single storey temporary prefabricated building and all associated site works

Description as published by the council. Its text starts part-way through a sentence.

This description may be shortened. The full text is in the council's planning file.

Location
Ballina, Co. Tipperary Map
Planning reference
18600758

Numbers and dates

Project type
Temporary/event
Received
14 Jun 2018
Decision to grant
7 Aug 2018
Final grant
11 Sep 2018
Site start notified
23 Oct 2018

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 23 Oct 2018, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 18600758 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Tipperary County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 23 Oct 2018Notice filed · Single storey temporary prefabricated building and all associated site worksView the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Ballina

Get alerts for BallinaFree. We email you when new applications appear.

Free email alerts

Get new Ballina projects by email

New applications, decisions and site starts in Ballina, Co. Tipperary. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options