Key facts
- Planning application 18601019 at Ardan Rua, Nenagh, Co Tipperary: 27 homes.
- It was received by Tipperary County Council on 16 Aug 2018.
- Status: Granted 11 Dec 2018 (final grant issued 23 Jan 2019).
Source: the Tipperary County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Nenagh · Planning applications in Co. Tipperary
Council register
The council's register shows: Granted on 11 Dec 2018.
Search the Tipperary planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
27 homes
construction of the final phase of the Ardan Rua housing development, approved under Planning Ref Nos 05510311, 07510461 & 13510054 and extension of duration Ref 11510020 & 12510135. Additionally, 11 other houses in Ardan Rua are being considered under Ref No 18600778. This phase of the development consists of 7 detached & 20 semi-detached houses (27 houses), connection to the public services, roads, footpaths, open space areas & ancillary site development works
- Location
- Nenagh, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 18601019
Numbers and dates
- Homes
- 27
- Floor area
- 2,968 m²
- Estimated construction value
- €4.5m to €5.7mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Large residential
- Received
- 16 Aug 2018
- Decision to grant
- 11 Dec 2018
- Final grant
- 23 Jan 2019
- Site start notified
- 6 Apr 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Site history
This site's history
-
Earlier permission 18600778 for this site: granted 24 Sep 2018, commencement notice filed for a start on 21 May 2019.
construction of the next phase of houses at the Ardan Rua housing development approved under planning references 05/51/0311, 07/51/0461 and… Named in this application's description
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 18601019 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Tipperary County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 6 Apr 2023Notice filed · Construction 7 no new dwelling houses, nos. 52 to 54, 75 to 78 (all inclusive) Ardan...Notice re-filed 31 May 2023 for the same works.View the site start
- Completion certificate recordedRecorded in May 2023 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
- Completion certificate recordedRecorded in May 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.