- Planning application 21110 at Saint Joseph's College, Clonmel Road, Carrick-on-Suir, Co. Tipperary: Demolition of the former St. Joseph’s College and associated…
- It was received by Tipperary County Council on 3 Feb 2021.
- Status: Granted 13 Dec 2021 (final grant issued 31 Jan 2022).
Source: the Tipperary County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Carrick-On-Suir · Planning applications in Co. Tipperary
Council register
The council's register shows: Granted on 13 Dec 2021.
Search the Tipperary planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Demolition of the former St. Joseph’s College and associated…
the demolition of the former St. Joseph’s College and associated outbuildings and the construction of a new 2-storey 8-classroom school building with a total floor area of 1,627 m² and incorporating a general purpose hall, a library resource area, staff rooms, support teaching spaces and all ancillary accommodation. The building will also include 34 no. photovoltaic panels and rainwater harvesting tanks at roof level. Works to the new school grounds will consist of the provision of a ball court, senior and junior play areas, kick about and orchard and nature areas and associated hard and soft landscaping throughout. The development will also include the widening of the road along the North Quay, drop-off and pick-up areas for both cars and buses, the provision of 16 no. car parking spaces (including 1 no. disabled parking space), sheltered bicycle stands, public realm works to include new paving on Clonmel/Well Road and North Quay, with new entrances, gates and boundary treatments, flood storage compensation area, and all other associated site and development works. A Natura Impact Statement (NIS) has been prepared and will be submitted to the planning authority with the application
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Carrick-On-Suir, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 21110
Numbers and dates
- Floor area
- 1,627 m²
- Project type
- Infrastructure
- Received
- 3 Feb 2021
- Decision to grant
- 13 Dec 2021
- Final grant
- 31 Jan 2022
- Site start notified
- 30 Nov 2023
Timeline
- Application received
- Decision to grant
- Appeal lodged
- Appeal decidedAppeal withdrawn S.140(1)(a)
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 21110 on eplanning.ie: drawings, reports and the decision.Open the council's file
- AppealAppeal withdrawn S.140(1)(a) · 312415 / 27 Jan 2022View the appeal record
How we know this
From the Tipperary County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 30 Nov 2023Notice filed · The demolition of the former St. Joseph's College and associated outbuildings and the...View the site start
- Completion certificate recordedRecorded in Nov 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.