Site start · Co. Tipperary
Thurles, Tipperary
Granted 3 Aug 2023 (final grant issued 6 Sep 2023)
Key facts
- Site start record 2360405 at Thurles, Co. Tipperary: Demolition/removal of existing structures.
- The planning authority is Tipperary County Council.
- Status: Granted 3 Aug 2023 (final grant issued 6 Sep 2023).
Source: the Tipperary County Council planning register, as last seen on 12 Jul 2026. Open the council's file
More planning applications in Thurles · Planning applications in Co. Tipperary
Council register
The council's register shows: Granted on 3 Aug 2023.
Search the Tipperary planning register
Application details as we last saw them in the national register on 12 Jul 2026.
What and where
Demolition/removal of existing structures
(1) the demolition/removal of existing structures including 1 no. storage container, gates, signage, dispensing pumps, gantry and bottom loading skid on site; (2) the change of use of an existing warehouse (unit 1) to office space and the change of use of an existing office building (unit 2) to provide ancillary storage space; (3) elevational changes to the existing warehouse (unit 1); 4) the construction of an unmanned fuel service station consisting of a) 2 no. fuel pumps with canopy over, dispensing fuel on each side and b) the erection of 1 no. totem sign; and 5) all associated ancillary development works including vehicular access, the closure of 1 no. existing entrance), boundary treatments, landscaping, drainage, plant and services area, and vehicular and bicycle parking
- Location
- Thurles, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 2360405
- Application type
- Commencement Notice
- Owner named on the notice
- East Cork Oil Company Unlimited Company
Numbers and dates
- Project type
- Commercial fit-out
- Received
- 14 Jun 2023
- Decision to grant
- 3 Aug 2023
- Final grant
- 6 Sep 2023
- Site start notified
- 8 Aug 2024
Documents and evidence
Check the record
- Council planning fileThe application file 2360405 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Tipperary County Council planning register, as last seen on 12 Jul 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 8 Aug 2024Notice filed · Material change of use and material alteration, from storage use to office use, of...View the site start
- Completion certificate recordedRecorded in Aug 2024 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.