Commencement

1 dwelling, Ardfinnan, Tipperary - Planning Application 2460224

Tipperary / Ardfinnan / Ardfinnan, Tipperary

Est. value €250k–500k
Units 1
Floor area 242 m²
Commenced 23 Sep 2024

Source-linked planning record

1 dwelling, Ardfinnan, Tipperary - Planning Application 2460224

Tipperary / Ardfinnan / Ardfinnan, Tipperary
PB ref
PB-419436
Plan ref
2460224
Authority
Tipperary County Council
Stage / date
Commencement / 23 Sep 2024
Est. value band
€250k–500k
Units / floor
1 / 242 m²
Project class
Infrastructure
Promoter
Marlhill Construction Services Ltd
Architect / agent
Marlhill Construction Services Ltd

Source: http://www.eplanning.ie/TipperaryCC/AppFileRefDetails/2460224/0

Key facts

Lead summary

Source
Owner-supplied commencement export
Planning authority
Tipperary County Council
Application reference
2460224
Applicant
Marlhill Construction Services Ltd
Agent
Marlhill Construction Services Ltd
Decision stage
Commencement
Commenced
23 Sep 2024
Units
1
Floor area
242 m²
Builder / developer
Marlhill Construction Services Ltd

Official description

Verbatim source text

the construction of a bungalow with all associated site works including installation of a wastewater treatment plant with tertiary system, site road, relocation of shed on site, and for the indefinite retention of single storey detached building being used as a home office. Access to the site will be via existing entrance and access road

Verify against official source

Project team

Named source parties

Promoter
Marlhill Construction Services Ltd
Planning agent
Marlhill Construction Services Ltd
Builder / developer
Marlhill Construction Services Ltd

Lifecycle timeline

Application to site progress

  1. Applied

    28 Mar 2024 2460224
  2. Decision

    Conditional 15 Jul 2024
  3. Appeal

    No appeal indexed No public appeal record is indexed against this application.
  4. Commenced

    23 Sep 2024 Work started · Erection of dwelling
  5. Completed

    Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.

Likely trades & supplier leads

Inferred from scheme type and scale

ComplianceElectricalGroundworksHealth & SafetyMain contractorMechanical
Board this lead Create alert