Small multi-unit · Co. Tipperary
Rosehill Estate Clonbealy, Newport, Co. Tipperary
Granted 8 Sep 2025 (final grant issued 12 Oct 2025)
Key facts
- Planning application 2560353 at Rosehill Estate Clonbealy, Newport, Co. Tipperary: 4 homes.
- The applicant is ABBEY VIEW QUIN PROPERTY DEVELOPMENT LTD.
- It was received by Tipperary County Council on 24 Apr 2025.
- Status: Granted 8 Sep 2025 (final grant issued 12 Oct 2025).
- Work was due to start on 4 Aug 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Tipperary County Council planning register, checked 2 Jun 2026. Open the council's file
More planning applications in Newport · Planning applications in Co. Tipperary
What and where
4 homes
the construction of 4 no. two-storey semi-detached dwelling houses, site entrances and ancillary site works
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Newport, Co. Tipperary Map
- Council
- Tipperary County Council
- Planning reference
- 2560353
Numbers and dates
- Homes
- 4
- Floor area
- 525 m²per planning documents
- Estimated construction value
- €790k to €1.1mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Small multi-unit
- Received
- 24 Apr 2025
- Decision to grant
- 8 Sep 2025
- Final grant
- 12 Oct 2025
- Site start notified
- 4 Aug 2026
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 2560353 on eplanning.ie: drawings, reports and the decision.Open the council's file
- From the planning documentsRead from Application Form - Part A in the council's file.
- Unit mix
- 4 3 Bed
- Floor area
- 525 m² (per planning documents)
- Site area
- 0.17 ha
- Applicant in the planning documents
- ABBEY VIEW QUIN PROPERTY DEVELOPMENT LTD
- Scope
- Construction of 4 no. two-storey semi-detached dwelling houses, site entrances and ancillary site works.
How we know this
From the Tipperary County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.
Site starts
Commencement notices for this permission
- 4 Aug 2026Notice filed · CONSTRUCTION OF 2 NO. 2-STOREY SEMI-DETACHED DWELLINGS AND 1 NO 2-STOREY DETACHED DWELLINGView the site start