Large residential · Co. Tipperary

Prior Park Grove, Clonmel, Co. Tipperary

Granted 3 Dec 2025 (final grant issued 15 Jan 2026)

Get updates on this application

We'll email you when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2560701 at Prior Park Grove, Clonmel, Co. Tipperary: 21 homes.
  • The applicant is Hallclon Properties Ltd (In Receivership. The agent is Halley Murphy & Associates.
  • It was received by Tipperary County Council on 18 Jul 2025.
  • Status: Granted 3 Dec 2025 (final grant issued 15 Jan 2026).
  • Work started on site on 28 Apr 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Tipperary County Council planning register, checked 2 Jun 2026. Open the council's file

More planning applications in Clonmel · Planning applications in Co. Tipperary

What and where

21 homes

the construction of 21 no. residential units comprising: 2 no. two-storey, three-bedroom semi-detached houses; 10 no. two-storey, three-bedroom terraced/end-of-terrace houses; and 9 no. two-storey, two-bedroom terraced/end-of-terrace houses, to complete the development previously approved under Planning Ref. PL 52.227298/06550157 (now expired). The development includes all associated site works and infrastructure services

Description as published by the council. Its text starts part-way through a sentence.

Location
Clonmel, Co. Tipperary Map
Planning reference
2560701
Applicant
Hallclon Properties Ltd (In Receivership
Council planning fileGet alerts

Numbers and dates

Homes
21
Floor area
1,980 m²per planning documents
Estimated construction value
€3.0m to €3.8mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
Project type
Large residential
Received
18 Jul 2025
Decision to grant
3 Dec 2025
Final grant
15 Jan 2026
Site start
28 Apr 2026

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start

Site history

This site's history

  1. Earlier planning reference 06550157, named in this application's description: work started 25 Dec 2018.

    Named in this application's description

Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.

Outlook

What happens next

Work started on site on 28 Apr 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Services and drainageNamed in the application description
  • RoofingNamed in the planning documents
  • Windows/doorsNamed in the planning documents

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2560701 on eplanning.ie: drawings, reports and the decision.Open the council's file
  • From the planning documentsRead from Application Form - Part A in the council's file.
    Unit mix
    9 2-bed, 12 3-bed
    Floor area
    1,980 m² (per planning documents)
    Site area
    0.691 ha
    Scope
    Construction of 21 residential units (2 and 3-bed houses) with associated site works and infrastructure to complete a previously approved development.
    Roofing
    “Selected concrete roof tile on treated timber battens on Tyvek underfelt on prefabricated timber trusses”
    Windows/doors
    “uPVC double glazed windows and composite doors”

How we know this

From the Tipperary County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.

Site starts

Commencement notices for this permission

  1. 28 Apr 2026Work started · Build 21 dwelling housesView the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Clonmel

Get alerts for ClonmelFree. We email you when new applications appear.

Free email alerts

Get new Clonmel projects by email

New applications, decisions and site starts in Clonmel, Co. Tipperary. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options