Togher More, Roundwood Village, Roundwood, Co. Wicklow
Under appeal since 23 Jun 2021 (Granted 28 May 2021 by the council)
We no longer update this application, so we can't email you about it. Get new planning applications in Roundwood by email
Key facts
- Planning application 201087 at Togher More, Roundwood Village, Roundwood, Co. Wicklow: Demolition of the existing agricultural shed and the construction…
- It was received by Wicklow County Council on 28 Oct 2020.
- Status: Under appeal since 23 Jun 2021 (Granted 28 May 2021 by the council).
Source: the Wicklow County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Roundwood · Planning applications in Co. Wicklow
Council register
The council's register shows: Granted on 28 May 2021.
Appealed to An Coimisiún Pleanála on 23 Jun 2021.
Search the Wicklow planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Demolition of the existing agricultural shed and the construction…
the demolition of the existing agricultural shed (12 sq m) and the construction of a mixed-use development comprising 59 no. residential units (10 no. four bedroom houses, 37 no. three bedroom houses, 2 no. two bedroom houses, 1 no. three bedroom apartment, 6 no. two bedroom apartments and 3 no. one bedroom apartments) and 4 no. commercial units (95.8 sq m, 224.35 sq m, 125.95 sq m and 140.79 sq m) to accommodate a mix of uses to include a café, 2 no. retail units (Class 1) and medical or health services (Class 8). The commercial uses will be clustered around a proposed 'village green' (345 sq m) which is connected to the Main Street. The development will also include the repositioning of the existing access to the site, 137 no. ancillary car parking spaces; hard and soft landscaping including ancillary allotments; lighting; balconies facing South, East and West; solar panels; boundary treatments; ESB substation; changes in level; and all associated site development works above and below ground. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development and will be submitted to the Planning Authority with this Planning Application
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Roundwood, Co. Wicklow Map
- Council
- Wicklow County Council
- Planning reference
- 201087
Numbers and dates
- Project type
- Infrastructure
- Received
- 28 Oct 2020
- Council decision
- 28 May 2021
- Appeal lodged
- 23 Jun 2021
- Site start notified
- 8 Sep 2022
Timeline
- Application received
- Granted by the council
- Appeal lodged
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 201087 on eplanning.ie: drawings, reports and the decision.Open the council's file
- AppealUnder appeal · 310620 / 23 Jun 2021View the appeal record
How we know this
From the Wicklow County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 8 Sep 2022Notice filed · phase 1 · The construction of 5 no. residential units...View the site start
- 8 Jan 2024Notice filed · phase 2 · The construction of 23No. residential units (1No. 2-bed, 18No. 3-bed, 4No. 4-bed) and...View the site start
- 15 Apr 2024Notice filed · phase 3 · Construction of Block A - two-storey mixed-use development consisting of 2No. retail...View the site start
- Completion certificate recordedRecorded in Jan 2024 · 17 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.