Save this project to account
Connected planning records

Planning case FW15A0067

Fingal County Council · FW15A0067 · Blanchardstown Road North, Blanchardstown, Dublin

Latest linked evidence

Notified commencement · 2015-11-14

The proposed development represents Phase 2 of Alexion’s biopharmaceutical manufacturing campus and includes 6 no. buildings with a total floor area of 30,994 square metres, together with external utility areas and associated site works. The development provides for the following:- a four-storey 21,869 square metre and 42.5 metre high manufacturing building including intermediate level mezzanines and boiler flue stack (to 48.5 metres height); a single-storey 3,626 square metre and 16 metre high warehouse extension; a two-storey 4,563 square metre and 13.5 metre high central utilities building; a utilities yard and wastewater treatment area. The ancillary external utilities within the utility yard will consist of; a single storey control building, single storey pump house, single-storey drum storage building, single storey electrical building, process water and waste water storage tanks, bunded water treatment chemical tanks, bunded fuel storage tank and back-up electrical generators; each of these facilities will be accessible via a single-storey internal access corridor running through the spine of the campus with elevated utility rack. The development also includes:- a staff entrance lobby extension to the western elevation of the Phase 1 internal access corridor; car parking for an additional 220 vehicles; an electrical substation building with separate access off Cruiserath Road; continued provision of temporary construction access off Cruiserath Road to be maintained as

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    FW15A0067

    Official source

  2. Planning decision

    FW15A0067

    Permission granted

    Official source

  3. Grant date recorded

    FW15A0067

    Official source

  4. Notified commencement

    Commencement notice

    Enabling works and bulk excavation for Phase 2 of Alexion’s biopharma manufacturing campus. No foundations or other building works are included in the works covered by this Commencement Notice. The enabling works will clear the site and form a new construction compound for subsequent building works. The enabling works also includes site hoarding, a stoned working platform for the subsequent building works and the provision of site access roads and temporary car parking areas. The bulk excavation will reduce the site levels to those appropriate for the subsequent building works. Drawing numbers IE-DR-0210, IE-DR-0220 and IE-DR-0230 show the nature and extent of the works covered by this Commencement Notice. A separate Commencement Notice “with documentation” will be submitted in advance of the commencement of the subsequent building works.

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    The proposed development represents Phase 2 of Alexion’s biopharmaceutical manufacturing campus and includes 6 no. buildings with a total floor area of 30,994 square metres, together with external utility areas and associated site works. The development provides for the following:- a four-storey 21,869 square metre and 42.5 metre high manufacturing building including intermediate level mezzanines and boiler flue stack (to 48.5 metres height); a single-storey 3,626 square metre and 16 metre high warehouse extension; a two-storey 4,563 square metre and 13.5 metre high central utilities building; a utilities yard and wastewater treatment area. The ancillary external utilities within the utility yard will consist of; a single storey control building, single storey pump house, single-storey drum storage building, single storey electrical building, process water and waste water storage tanks, bunded water treatment chemical tanks, bunded fuel storage tank and back-up electrical generators; each of these facilities will be accessible via a single-storey internal access corridor running through the spine of the campus with elevated utility rack. The development also includes:- a staff entrance lobby extension to the western elevation of the Phase 1 internal access corridor; car parking for an additional 220 vehicles; an electrical substation building with separate access off Cruiserath Road; continued provision of temporary construction access off Cruiserath Road to be maintained as

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.