Market signals

Housing starts: inspect the monthly evidence

Follow each monthly figure to its notice, counting rule and official evidence.

Selected month2026-04

Closed calendar month

Included phase units722

Source-stated units with explicit holds

Published figure3,187

Includes scheme figures and older estimates

Source rows1,403

1,236 held or unknown

A commencement notice says work is starting; it is not a completion. Phase figures, whole-scheme figures and older estimates are shown separately. Some notices may repeat the homes on another notice.

Data to 13 November 2026. Checked 15 November 2026. A finished calendar month may still be missing some notices.

Month membership uses the validation date, then submitted date, then notified commencement date when the earlier field is absent. This preserves the existing published measure; a notified start can fall in another month.

Months

Choose a month

current product months and the September 2025 comparison
MonthPublished unitsIncluded phase unitsPeriod
2026-111,8991,899In progress
2026-103,2083,204Closed calendar month
2026-094,1194,107Closed calendar month
2026-084,1654,036Closed calendar month
2026-074,1634,085Closed calendar month
2026-064,3383,804Closed calendar month
2026-052,744794Closed calendar month
2026-043,187722Closed calendar month
2026-036,6341,121Closed calendar month
2026-024,9831,098Closed calendar month
2026-015,3641,757Closed calendar month
2025-128,8251,857Closed calendar month
2025-093,240436Closed calendar month

Contribution bridge

2026-04: how the figures relate

zero difference for the stated ledger metric; legacy differences remain explicit
Measure / holdUnits
Source-stated phase units included722
Older estimate or unconfirmed scope2,397
Possible repeated phase: same project, start date and units44
Stored official phase evidence could not confirm this value23
No unit quantity stated0
Whole-scheme figure; not counted as another phase1
Current source-row sum3,187
Published figure3,187
Unresolved published/source difference0

Record-level reconciliation

What explains the difference

Calculated from this retained ledger; original figures unchanged

3,187 published units = 722 included phase units + 2,465 held source units + 0 unexplained published/source difference.

438 other held rows state no positive source quantity and add zero to this difference. The rule beside each record explains the hold; a whole-scheme hold is not a duplicate finding.

Held noticeMonth basis / notified startUnits heldExact counting ruleEvidence
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-15
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-13
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-20
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-16
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-10
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-14
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-09
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-15
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-15
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-06
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-18
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-20
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-20
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-09
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-03
47Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-14
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-14
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-18
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-20
1Older estimate or unconfirmed scopeNotice
Commencement notice2026-04-01 · Validation date
Notified start 2026-04-20
1Older estimate or unconfirmed scopeNotice

Inspect all 798 positive-quantity held records

167 included rows connect to 144 verified project identities. 1,114 rows lack a project destination and 0 lack a public notice page. They remain in the source reconciliation. Locations are not assessed by this ledger.

All source rows · Included phase contributions · Held and unknown

Download all month rows (CSV) · Month evidence (JSON)

Inspect all preserved monthly figures and evidence availability

Counted values and evidence

2026-04: notices and contributions

50 rows per page; downloads contain all rows
Notice / authorityDatesSeparate source quantitiesCounted unitsRule / holdRecords
Commencement notice
Kildare County Council
2026-04-01
Validation date
Notified start 2026-04-15
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Meath County Council
2026-04-01
Validation date
Notified start 2026-04-13
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Tipperary County Council
2026-04-01
Validation date
Notified start 2026-04-20
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Cork County Council
2026-04-01
Validation date
Notified start 2026-04-16
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project link unresolved
Commencement notice
Louth County Council
2026-04-01
Validation date
Notified start 2026-04-10
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Cork County Council
2026-04-01
Validation date
Notified start 2026-04-14
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project
Commencement notice
Roscommon County Council
2026-04-01
Validation date
Notified start 2026-04-09
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Dublin City Council
2026-04-01
Validation date
Notified start 2026-04-15
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project page not confirmed
Commencement notice
Kildare County Council
2026-04-01
Validation date
Notified start 2026-04-16
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project page not confirmed
Commencement notice
Wexford County Council
2026-04-01
Validation date
Notified start 2026-04-13
Phase 4
Scheme 4
4Source-stated phase unitsNotice
Project
Commencement notice
Meath County Council
2026-04-01
Validation date
Notified start 2026-04-15
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Dublin City Council
2026-04-01
Validation date
Notified start 2026-04-20
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project page not confirmed
Commencement notice
Donegal County Council
2026-04-01
Validation date
Notified start 2026-04-15
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Donegal County Council
2026-04-01
Validation date
Notified start 2026-04-15
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Commencement notice
Kildare County Council
2026-04-01
Validation date
Notified start 2026-04-06
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Wexford County Council
2026-04-01
Validation date
Notified start 2026-04-18
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project
Commencement notice
Laois County Council
2026-04-01
Validation date
Notified start 2026-04-20
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Donegal County Council
2026-04-01
Validation date
Notified start 2026-04-20
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project link unresolved
Commencement notice
Dublin City Council
2026-04-01
Validation date
Notified start 2026-04-14
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project page not confirmed
Commencement notice
South Dublin County Council
2026-04-01
Validation date
Notified start 2026-04-07
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project
Commencement notice
Roscommon County Council
2026-04-01
Validation date
Notified start 2026-04-09
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project link unresolved
Commencement notice
Kildare County Council
2026-04-01
Validation date
Notified start 2026-04-10
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project page not confirmed
Commencement notice
Wicklow County Council
2026-04-01
Validation date
Notified start 2026-04-03
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Cavan County Council
2026-04-01
Validation date
Notified start 2026-04-07
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project page not confirmed
Commencement notice
Dun Laoghaire Rathdown County Council
2026-04-01
Validation date
Notified start 2026-04-13
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project page not confirmed
Commencement notice
Offaly County Council
2026-04-01
Validation date
Notified start 2026-04-14
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Waterford City and County Council
2026-04-01
Validation date
Notified start 2026-04-14
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Dublin City Council
2026-04-01
Validation date
Notified start 2026-04-18
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Offaly County Council
2026-04-01
Validation date
Notified start 2026-04-20
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Tipperary County Council
2026-04-01
Validation date
Notified start 2026-04-20
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Clare County Council
2026-04-01
Validation date
Notified start 2026-04-17
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Sligo County Council
2026-04-01
Validation date
Notified start 2026-04-14
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Westmeath County Council
2026-04-01
Validation date
Notified start 2026-03-12
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Offaly County Council
2026-04-01
Validation date
Notified start 2026-04-20
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Dublin City Council
2026-04-01
Validation date
Notified start 2026-04-15
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project page not confirmed
Commencement notice
Kerry County Council
2026-04-01
Validation date
Notified start 2026-04-15
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project link unresolved
Commencement notice
Cork County Council
2026-04-01
Validation date
Notified start 2026-04-23
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project
Commencement notice
Donegal County Council
2026-04-01
Validation date
Notified start 2026-04-16
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Cork County Council
2026-04-01
Validation date
Notified start 2026-04-16
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project
Commencement notice
Mayo County Council
2026-04-01
Validation date
Notified start 2026-04-10
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Tipperary County Council
2026-04-01
Validation date
Notified start 2026-04-20
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Dublin City Council
2026-04-01
Validation date
Notified start 2026-04-15
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project page not confirmed
Commencement notice
Tipperary County Council
2026-04-01
Validation date
Notified start 2026-04-07
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Commencement notice
Limerick City and County Council
2026-04-01
Validation date
Notified start 2026-04-15
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project
Commencement notice
Dublin City Council
2026-04-01
Validation date
Notified start 2026-04-14
Phase not stated
Scheme not stated
0No unit quantity statedNotice
Project link unresolved
Commencement notice
Wicklow County Council
2026-04-01
Validation date
Notified start 2026-04-20
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Westmeath County Council
2026-04-01
Validation date
Notified start 2026-04-10
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Commencement notice
Roscommon County Council
2026-04-01
Validation date
Notified start 2026-04-15
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed
Commencement notice
Donegal County Council
2026-04-01
Validation date
Notified start 2026-04-16
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Commencement notice
Galway County Council
2026-04-01
Validation date
Notified start 2026-04-10
Phase not stated
Scheme not stated
0Older estimate or unconfirmed scopeNotice
Project page not confirmed

Page 1 of 29 · 1,403 rows in this view · Next rows

Each row links to its PlanningBrief notice and project pages where they exist. A missing indexed record or quantity remains an explicit exception.