Infrastructure, Thurles, Tipperary - Planning Application 2460829
Tipperary / Thurles / Thurles, Tipperary
Source-linked planning record
Infrastructure, Thurles, Tipperary - Planning Application 2460829
Tipperary / Thurles / Thurles, Tipperary- PB ref
- PB-418157
- Plan ref
- 2460829
- Authority
- Tipperary County Council
- Stage / date
- Commencement / 2 Feb 2026
- Est. value band
- Value not disclosed
- Project class
- Infrastructure
- Promoter
- not available yet
- Architect / agent
- Martin Reddin Ltd
Source: http://www.eplanning.ie/TipperaryCC/AppFileRefDetails/2460829/0
Key facts
Lead summary
- Source
- Owner-supplied commencement export
- Planning authority
- Tipperary County Council
- Application reference
- 2460829
- Applicant
- not available yet
- Agent
- Martin Reddin Ltd
- Decision stage
- Commencement
- Commenced
- 2 Feb 2026
- Builder / developer
- Martin Reddin Ltd
Official description
Verbatim source text
the development of a single storey drive-thru restaurant including the ancillary sale of hot food for consumption off the premises with an associated corral area, elevational signage, modifications to existing vehicular access off the Thurles Relief Road, car parking including accessible parking spaces, grill bays, EV charging spaces, bicycle parking, a height restrictor, customer order points with associated canopies, totem signage, free-standing signage, banner frames and digital menu boards, ESB substation and kiosk, landscaping including outdoor furniture/seating area with parasols, boundary treatments, lighting, and all associated site and engineering works necessary to facilitate the development. A Natura Impact Statement (NIS) has been prepared and is submitted to the planning authority with the application
Verify against official sourceMore Tipperary planning activity
These are county discovery links, not claimed relationships to this application.
Project team
Named source parties
- Promoter
- not available yet
- Planning agent
- Martin Reddin Ltd
- Builder / developer
- Martin Reddin Ltd
Lifecycle timeline
Application to site progress
-
Commenced
2 Feb 2026 Work started · The construction of the provision of a 478.8 sq. m. single storey drive-thru restaurant... -
Completed
Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.
Likely trades & supplier leads