New build
23 May 2023 · Latest notice
2 notices · phased
Glanmire, Cork · Cork City Council · Planning ref 21/40507
Construction of 3no. three storey buildings comprising 30no. dwelling units at Ashbrook, Riverstown, Glanmire, Cork. [Unit Nos 1-30]
Notice identity Works stated Scale Commenced
CN0100945CY BCMS open-data feed
Construction of 3no. three storey buildings comprising 30no. dwelling units at Ashbrook, Riverstown, Glanmire, Cork. [Unit Nos 1-30]
30 units · 2,630.3 m²Builder not named
23 May 2023
CN0099508CY BCMS owner-supplied export
Construction of 3no. three storey buildings comprising 30no. dwelling units at Ashbrook, Riverstown, Glanmire, Cork. [Unit Nos 1-30]
30 units · 2,630.3 m²Builder named
11 Apr 2023
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
22 May 2023 · Latest notice
3 notices · phased
Kilcock, Kildare · Kildare County Council · Planning ref 21/365
Construction of 66no. Dwellings at Oughteranny Village, Branganstown, Kilcock, Co. Kildare.
Notice identity Works stated Scale Commenced
CN0100703KE BCMS open-data feed
Construction of 66no. Dwellings at Oughteranny Village, Branganstown, Kilcock, Co. Kildare.
66 units · 8,116.6 m²Builder not named
22 May 2023
CN0098941KE BCMS owner-supplied export
Construction of 66no. Dwellings at Oughteranny Village, Branganstown, Kilcock, Co. Kildare.
66 units · 8,114.2 m²Builder named
24 Mar 2023
CN0094261KE BCMS owner-supplied export
Con struction of 66no. Dwellings at Oughteranny Village, Branganstown, Kilcock, Co. Kildare.
66 units · 8,135.7 m²Builder not named
29 Sep 2022
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
19 May 2023 · Latest notice
2 notices · phased
Ballisodare, Sligo · Sligo County Council · Planning ref 22/167
construction of 21 residential units with all associated siteworks
Notice identity Works stated Scale Commenced
CN0100912SO BCMS open-data feed
Construction of 21 new Dwelling units, with all associated site works
21 units · 2,708.7 m²Builder not named
19 May 2023
CN0098138SO BCMS owner-supplied export
construction of 21 residential units with all associated siteworks
21 units · 2,708.7 m²Builder named
06 Mar 2023
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
19 May 2023 · Latest notice
2 notices · phased
Midleton, Cork · Cork County Council · Planning ref 176604
The project comprises the development of 65 no houses (No 1-65, Rock Gate) including 54 no semi- detached & 11 no detached units on a greenfield site in Baneshane, Midleton, Co. Cork, and all associated ancillary development works including access, parking, drainage (including pumping station), and landscaping.
Notice identity Works stated Scale Commenced
CN0100877CC BCMS open-data feed
The project comprises the development of 65 no houses (No 1-65, Rock Gate) including 54 no semi-detached & 11 no detached units on a greenfield site in Baneshane, Midleton, Co. Cork, and all associated ancillary development works including access, parking, drainage (including pumping station), and landscaping.
65 units · 9,499 m²Builder not named
19 May 2023
CN0097889CC BCMS owner-supplied export
The project comprises the development of 65 no houses (No 1-65, Rock Gate) including 54 no semi- detached & 11 no detached units on a greenfield site in Baneshane, Midleton, Co. Cork, and all associated ancillary development works including access, parking, drainage (including pumping station), and landscaping.
65 units · 9,499 m²Builder named
22 Feb 2023
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
03 May 2023 · Latest notice
5 notices · phased
Dublin, Dublin · Fingal County Council · Planning ref SHD/009/19
Block C Claremont Howth, Proposed Construction of Residential/Mixed Use Development, Block C at Former Techrete Site/Beshoff Motors & Garden Centre, Howth Road, Howth, Co. Dublin
Notice identity Works stated Scale Commenced
CN0100350FL BCMS owner-supplied export
Block B Claremont Howth, Proposed Construction of Residential Developement, Former Techrete Site/BeshoffMotors & Garden Centre, Howth Road, Howth, Co. Dublin
154 units · 11,564.9 m²Builder named
03 May 2023
CN0100353FL BCMS owner-supplied export
Block C Claremont Howth, Proposed Construction of Residential/Mixed Use Development, Block C at Former Techrete Site/Beshoff Motors & Garden Centre, Howth Road, Howth, Co. Dublin
83 units · 8,131.5 m²Builder named
03 May 2023
SN0006088FL BCMS open-data feed
Block B, C & D Basement, Former Techrete Site/BeshoffMotors & Garden Centre, Howth Road, Howth, Co. Dublin, Proposed construction of a single-storey basement car park with associated exits forming part of a future residential development – Block B, C & D
278 units · 15,593.5 m²Builder not named
25 May 2021
SN0006067FL BCMS open-data feed
Proposed construction of a single-storey basement car park with associated exits forming part of a future residential development – Block A Block A Basement, Former Techrete Site/BeshoffMotors & Garden Centre, Howth Road, Howth, Co. Dublin
234 units · 6,143.1 m²Builder not named
24 May 2021
CN0071348FL BCMS owner-supplied export
Enabling works to include: Hoarding install, Asbestos removal and site clearance, Soft Strip, Heavy Demolition of buildings, Removal of hard standing areas, Install Piling Mat, Install Temporary Piles to facilitate basement excavation and Bulk dig for basement works
234 units · 48,251.9 m²Builder named
14 Dec 2020
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
18 Apr 2023 · Commenced
1 notice · 1 source identity
Co. Dublin, Dublin · Fingal County Council · Planning ref ABP-306102-19
Block A building Claremont Howth, Proposed Construction of Residential/Mixed Use Development, Former Techrete Site/BeshoffMotors & Garden Centre, Howth Road,Howth, Co. Dublin
New build
17 Apr 2023 · Latest notice
3 notices · phased
Ballincollig, Cork · Cork City Council · Planning ref P8.HCP.20.01
Construction of 64 no. residential units with car parking,communal landscape area and all associated site works.
Notice identity Works stated Scale Commenced
CN0099654CY BCMS open-data feed
Construction of 64 no. residential units with car parking, communal landscape area and all associated site works. This phase relates to Units 61 & 62 and 63 & 64 Gairdín Uí Ruacháin.
4 units · 287 m²Builder not named
17 Apr 2023
CN0098965CY BCMS owner-supplied export
Construction of 64 no. residential units with car parking, communal landscape area and all associated site works. This phase relates to Units 45 & 46 and 47 & 48 Gairdín Uí Ruacháin.
64 units · 281.3 m²Builder named
30 Mar 2023
CN0095566CY BCMS owner-supplied export
Construction of 64 no. residential units with car parking,communal landscape area and all associated site works.
64 units · 5,016.2 m²Builder named
18 Nov 2022
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
08 Apr 2023 · Latest notice
2 notices · phased
Kingscourt, Cavan · Cavan County Council · Planning ref 20/407
Construction of 20 no. two storey terraced houses, access to Kells Road, internal road, paths and associated site works on site no.'s 01 - 20, Cnoc na Rí, Kells Road, Kingscourt, Co. Cavan
Notice identity Works stated Scale Commenced
CN0099557CN BCMS owner-supplied export
Construction of 20 no. two storey terraced houses, access to Kells Road, internal road, paths and associated site works on site no.'s 01 - 20, Cnoc na Rí, Kells Road, Kingscourt, Co. Cavan
20 units · 1,965 m²Builder named
08 Apr 2023
CN0099094CN BCMS owner-supplied export
Construction of 20 no. two storey terraced houses, access to Kells Road, internal road, paths and associated site works on site no.'s 38 - 57, Cnoc na Rí, Kells Road, Kingscourt, Co. Cavan
20 units · 1,965 m²Builder named
23 Mar 2023
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
04 Apr 2023 · Latest notice
5 notices · phased
Newbridge, Kildare · Kildare County Council · Planning ref 16/975
Construction of Zone 1D, consisting of the erection of 43 number houses in total (1 No. Type A, four bedroom, two-storey semi-detached houses, 14 No. Type B, three bedroom, two-storey semi-detached houses, 15 No. Type B ‘h’, three bedroom, two-storey semi-detached houses, 1 No. Type B1, three bedroom, two-storey mid terrace house, 1 No. Type B2, three bedroom, two-storey semi-detached houses, 1 No. Type C, four bedroom, two-storey semi-detached house, 1 No. Type C‘h’, four bedroom, two-storey semi-detached house, 1 No. Type D, four bedroom, two-storey semi-detached house, 1 No. Type D ‘h’, four bedroom, two-storey semi-detached house, 3 No. Type G, two bedroom, two-storey terrace houses, 2 No. Type H, three bedroom, three-storey end terrace houses, 2 No. Type H ‘h’, three bedroom, three-storey end terrace houses). Associated public open space, landscaping, roads, parking and infrastructure, accessed off Station Road, Rickardstown, Newbridge, County Kildare.
Notice identity Works stated Scale Commenced
CN0099225KE BCMS owner-supplied export
Station Walk Creche (shell and core finish)
524 m²Builder named
04 Apr 2023
CN0082544KE BCMS open-data feed
Construction of Zone 1D, consisting of the erection of 43 number houses in total (1 No. Type A, four bedroom, two-storey semi-detached houses, 14 No. Type B, three bedroom, two-storey semi-detached houses, 15 No. Type B ‘h’, three bedroom, two-storey semi-detached houses, 1 No. Type B1, three bedroom, two-storey mid terrace house, 1 No. Type B2, three bedroom, two-storey semi-detached houses, 1 No. Type C, four bedroom, two-storey semi-detached house, 1 No. Type C‘h’, four bedroom, two-storey semi-detached house, 1 No. Type D, four bedroom, two-storey semi-detached house, 1 No. Type D ‘h’, four bedroom, two-storey semi-detached house, 3 No. Type G, two bedroom, two-storey terrace houses, 2 No. Type H, three bedroom, three-storey end terrace houses, 2 No. Type H ‘h’, three bedroom, three-storey end terrace houses). Associated public open space, landscaping, roads, parking and infrastructure, accessed off Station Road, Rickardstown, Newbridge, County Kildare.
43 units · 55,135.1 m²Builder not named
20 Oct 2021
CN0079983KE BCMS open-data feed
Construction of Zone 1C, consisting of the erection of 34 number houses in total (8 No. Type B, three bedroom, two-storey semi-detached houses, 9 No. Type B ‘h’, three bedroom, two-storey semi-detached houses, 1 No. Type B ‘end’, three bedroom, two-storey end terrace house, 1 No. Type B1, three bedroom, two-storey mid terrace house, 2 No. Type B2, three bedroom, two-storey semi-detached houses, 2 No. Type B2 ‘h’, three bedroom, two-storey semi-detached houses, 1 No. Type C, four bedroom, two-storey semi-detached house, 1 No. Type D ‘h’, four bedroom, two-storey semi-detached house, 5 No. Type G, two bedroom, two-storey terrace houses, 2 No. Type H, three bedroom, three-storey end terrace houses, 2 No. Type H ‘h’, three bedroom, three-storey end terrace houses). Associated public open space, landscaping, roads, parking and infrastructure, accessed off Station Road, Rickardstown, Newbridge, County Kildare.
34 units · 11,626.4 m²Builder not named
18 Aug 2021
CN0075313KE BCMS open-data feed
Construction of Zone 1B, consisting of the erection of 49 number houses in total (15 No. Type A, four bedroom, two-storey semi-detached house, 3 No. Type A1, four bedroom, two-storey semi-detached house, 21 No. Type B, three bedroom, two-storey end of terrace houses, 3 No. Type B1, three bedroom, two-storey mid terrace houses, 1 No. Type B2, three bedroom, two-storey semi-detached houses, 3 No. Type C, four bedroom, two-storey semi-detached house, 3 No. Type D, four bedroom, two-storey semi-detached houses). Associated public open space, landscaping, roads, parking and infrastructure, accessed off Station Road, Rickardstown, Newbridge, County Kildare.
49 units · 175,371 m²Builder not named
06 May 2021
CN0061620KE BCMS open-data feed
Construction of a two phased development consisting of a total of 361 number houses. Construction of Phase 1 of a four zone development, consisting of a total of 167 number houses. Construction of Zone 1A consists of a total of 34 number houses (1 No. Type A, four bedroom, two-storey semi-detached house, 1 No. Type A1, four bedroom, two-storey semi-detached house, 12 No. Type B, three bedroom, two-storey semi-detached houses, 8 No. Type B, three bedroom, two-storey end of terrace houses, 4 No. Type B1, three bedroom, two-storey mid terrace houses, 2 No. Type B2, three bedroom, two-storey semi-detached houses, 1 No. Type C, four bedroom, two-storey semi-detached house, 5 No. Type D, four bedroom, two-storey semi-detached houses). 1 No. electricity substation, associated public open space, landscaping, roads, parking and infrastructure, accessed off Station Road, Richardstown, Newbridge, County Kildare.
34 units · 4,964 m²Builder not named
17 Feb 2020
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
28 Mar 2023 · Latest notice
4 notices · phased
Ballybrack, Dublin · Dun Laoghaire Rathdown County Council · Planning ref ABP-300006-17
Construction of 8no. terraced units at Loughlinstown, Glenageary, County Dublin
Notice identity Works stated Scale Commenced
CN0099096DR BCMS owner-supplied export
Construction of 8no. terraced units at Loughlinstown, Glenageary, County Dublin
34 units · 6,937.6 m²Builder named
28 Mar 2023
CN0099108DR BCMS owner-supplied export
Block A Construction of 17no. units at Loughlinstown, Glenageary, County Dublin
34 units · 1,417 m²Builder named
28 Mar 2023
CN0099120DR BCMS owner-supplied export
Block B Construction of 17no. units at Loughlinstown, Glenageary, County Dublin
34 units · 1,417 m²Builder named
28 Mar 2023
CN0097974DR BCMS owner-supplied export
Enabling works, removing of existing planting, site compound for the construction of 42 units at Loughlinstown, Glenageary, Co. Dublin
42 units · 5 m²Builder named
21 Feb 2023
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
21 Mar 2023 · Latest notice
7 notices · phased
Naas, Kildare · Kildare County Council · Planning ref ABP-305416-19
Residential Development at Newtown, Kill, Co. Kildare- Phase 1 28 Housing Units
Notice identity Works stated Scale Commenced
CN0098720KE BCMS open-data feed
Block B Residential Development, Kill, Co. Kildare, Construction of a three storey block of 11no. apartments comprising 4no. 1 bed own hall door apartments and 1no. 2 bed own hall door apartment (ground floor), 4no. 2 bed duplex own hall door apartment units (first and second floor), 1no. 2 bed own hall door apartment unit with shared lobby (first floor) and 1no. 2 bed own hall door apartment (second floor).
11 units · 938 m²Builder not named
21 Mar 2023
CN0098724KE BCMS owner-supplied export
Block C Residential Development, Kill, Co. Kildare, Construction of a three storey block of 10no. apartments comprising 4no. 2 bed own hall door apartments (ground floor) and 6no. 2 bed maisonettes own hall door apartment units (first and second floor).
10 units · 942 m²Builder named
21 Mar 2023
SN0006870KE BCMS open-data feed
Construction of a two storey block of 4no. apartments numbers 21,22,23,24 Newtown Way.
4 units · 319 m²Builder not named
27 Jan 2022
SN0006871KE BCMS open-data feed
Construction of a two storey block of 4no. apartments numbers 25,26,27,28 Newtown Way.
4 units · 319 m²Builder not named
27 Jan 2022
CN0085006KE BCMS open-data feed
Residential Development at The Meadows, Kill, Co. Kildare. 75 Housing Units.
75 units · 8,333.5 m²Builder not named
05 Jan 2022
SN0006775KE BCMS open-data feed
Construction of a three storey block of 15no. apartments comprising 6no. 1 bed own hall door apartments (ground floor), 6no. 2 bed duplex own hall door apartment units (first and second floor), 1no. 2 bed own hall door apartment unit with shared lobby (ground floor), 1no. 2 bed own hall door apartment unit with shared lobby (first floor) and 1no. 2 bed own hall door apartment (second floor) on site nos. 03,04,05,06,07 and 08 Newtown Way and 07,08,09,10,11,12,13,14 and 15 Newtown Walk.
15 units · 1,253 m²Builder not named
13 Dec 2021
CN0071266KE BCMS owner-supplied export
Residential Development at Newtown, Kill, Co. Kildare- Phase 1 28 Housing Units
28 units · 3,068.3 m²Builder named
15 Dec 2020
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
16 Mar 2023 · Latest notice
4 notices · phased
Carrigaline, Cork · Cork County Council · Planning ref 20/05947
The demolition of existing 2 no. warehouse structures and the construction of 13 no. residential units (No's 1-13) including upgrades to the existing access road and modifications to the junction at Church Road and all associated site development works.
Notice identity Works stated Scale Commenced
SN0008241CC BCMS open-data feed
The demolition of existing 2 no. warehouse structures and the construction of 1 no. duplex unit (No's 14-17) including upgrades to the existing access road and modifications to the junction at Church Road and all associated site development works.
4 units · 304.4 m²Builder not named
16 Mar 2023
CN0098491CC BCMS owner-supplied export
The demolition of existing 2 no. warehouse structures and the construction of 11 no. residential units (No's 18-28) including upgrades to the existing access road and modifications to the junction at Church Road and all associated site development works.
11 units · 3,082.8 m²Builder named
14 Mar 2023
CN0098519CC BCMS open-data feed
The demolition of existing 2 no. warehouse structures and the construction of 10 no. residential units (No's 29-38) including upgrades to the existing access road and modifications to the junction at Church Road and all associated site development works.
10 units · 2,979.6 m²Builder not named
09 Mar 2023
CN0097901CC BCMS owner-supplied export
The demolition of existing 2 no. warehouse structures and the construction of 13 no. residential units (No's 1-13) including upgrades to the existing access road and modifications to the junction at Church Road and all associated site development works.
13 units · 30,303.0 m²Builder named
21 Feb 2023
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
03 Mar 2023 · Latest notice
11 notices · phased
Greystones, Wicklow · Wicklow County Council · Planning ref ABP-305773-19
It is proposed to construct a new residential development (Block 2) in the Charlesland area on the southern side of Greystones, Co. Wicklow. The development will consist of a 6-storey apartment block, served by two single escape stairs, with apartments located from ground to fifth floor. At ground floor it is proposed to provide amenity space, a bin store and electrical generator/store. All of the ancillary accommodation is access directly from the outside with the exception of the amenity space, which is provided with lobby protection and sprinkler protection as it communicates with the rest of the building.
Notice-stated scale
354 units · 14,656.2 m²
Notice-stated max
Highest notice-stated figure for each metric — notices are not summed.
Planning ref indexed
Builder not named
Notice identity Works stated Scale Commenced
SN0008172WW BCMS open-data feed
(There is an existing approved Fire Safety Certificate (Ref: BC 4293/2021) for the development, however) it is (now) proposed to carry out a fit out of this space on behalf of the Social Housing body who occupy the block to the Amenity Space at ground floor. A new meeting room, an electrical board, and a circulation corridor leading to a new kitchenette and WC are proposed, additionally a new final exit is proposed. Additionally, 6 new PV panels are proposed on the roof as part of the provisions for the amenity space.
84 units · 166.2 m²Builder not named
03 Mar 2023
SN0006934WW BCMS open-data feed
Duplex Block E - Units 06-17 Hawkins Wood Grove (12 Units in total) at Hawkins Wood, Greystones, Co. Wicklow.
12 units · 1,302.7 m²Builder not named
18 Feb 2022
SN0006450WW BCMS open-data feed
It is proposed to construct a new shell and core office development (Commercial Building 1A) in Glenheron C, Greystones, Co. Wicklow. The development will consist of a 2-storey office block served by two escape stairs.
1,376 m²Builder not named
24 Aug 2021
SN0006446WW BCMS open-data feed
It is proposed to construct a new shell and core office development (Enterprise Building 1) in Glenheron C, Greystones, Co. Wicklow. The development will consist of a 2-storey office block served by two escape stairs.
1,356 m²Builder not named
23 Aug 2021
SN0006238WW BCMS open-data feed
Duplex Block D - Units 56-67 Hawkins Wood Avenue (12 Units in total) at Hawkins Wood, Greystones, Co. Wicklow.
12 units · 1,302 m²Builder not named
05 Jul 2021
SN0006197WW BCMS open-data feed
Duplex Block C - Units 68-79 Hawkins Wood Avenue (12 Units in total) at Hawkins Wood, Greystones, Co. Wicklow.
12 units · 1,300 m²Builder not named
23 Jun 2021
SN0006092WW BCMS open-data feed
It is proposed to construct a new residential development (Block 2) in the Charlesland area on the southern side of Greystones, Co. Wicklow. The development will consist of a 6-storey apartment block, served by two single escape stairs, with apartments located from ground to fifth floor. At ground floor it is proposed to provide amenity space, a bin store and electrical generator/store. All of the ancillary accommodation is access directly from the outside with the exception of the amenity space, which is provided with lobby protection and sprinkler protection as it communicates with the rest of the building.
84 units · 8,537 m²Builder not named
19 May 2021
CN0075747WW BCMS open-data feed
Duplex Block A - Units 92-103 Hawkins Wood Avenue, Block B - Units 80-91 Hawkins Wood Avenue (24 Units in total) at Hawkins Wood, Greystones, Co. Wicklow.
24 units · 2,776 m²Builder not named
13 May 2021
SN0006037WW BCMS open-data feed
It is proposed to construct a new residential development (Block 1) in the Charlesland area in the southern side of Greystones, Co. Wicklow. The development will consist of a 6-storey apartment block, served by two single stairs, with apartments located from ground to fifth floor. At ground floor, it is proposed to provide ancillary accommodation, plant space, a bin store, and an electrical generator/store. The ancillary accommodation is accessed directly from the outside and will not communicate with the rest of the building.
90 units · 9,081 m²Builder not named
10 May 2021
CN0075630WW BCMS open-data feed
Units 1-55 Hawkins Wood Avenue, 1-8 Hawkins Wood Green, 1-21 Hawkins Wood Close, 1-35 Hawkins Wood Drive, 1-5 Hawkins Wood Grove, (124 Units in total) at Hawkins Wood, Greystones, Co. Wicklow.
124 units · 14,656.2 m²Builder not named
30 Apr 2021
CN0069948WW BCMS owner-supplied export
Proposed site development works relating to residential development (354 units) at Hawkins Wood, Greystones, Co. Wicklow.
354 unitsBuilder not named
02 Nov 2020
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
01 Mar 2023 · Latest notice
3 notices · phased
Gorey Hill, Wexford · Wexford County Council · Planning ref 20191472
The construction of 12 no. houses
Notice identity Works stated Scale Commenced
CN0098755WX BCMS owner-supplied export
The construction of 12 no. houses
36 units · 1,086 m²Builder named
01 Mar 2023
CN0082702WX BCMS open-data feed
Phase 2 of a Residential Development at Ramstown Gorey. Phase 2 consists of 20 no. houses set out in four terraces and made up of 11 no. 3-bed, 3 storey houses and 9 no. 2-bed, 2 storey houses and associated site works.
20 units · 21,246 m²Builder not named
28 Sep 2021
CN0080686WX BCMS owner-supplied export
construction of phase 01 of the housing development, as granted under planning ref. no. 20191472, which includes for the construction of 24no. dwellings, road entrance to existing public road, internal access road and footpaths, services, and ancillary site works.
36 units · 2,098 m²Builder named
01 Jun 2021
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
17 Feb 2023 · Commenced
1 notice · 1 source identity
Cork, Cork · Cork City Council · Planning ref P8.CNWQR.18.06
Description : Phase 1C, Cork Northwest Quarter Regeneration, Knocknaheeny: Construction of 41 Housing Units, consisting of 15 no. two-bedroom apartments in three storey buildings; 20 no. three storey three bedroom houses; 1 no. three storey four bedroom house; 5 no. two storey three bedroom houses; construction of a traversal avenue referred to as "BÓTHAR NA SILÍNÍ"/Spine Road; associated site works and landscaping.
New build
17 Feb 2023 · Latest notice
4 notices · phased
Barraduff, Kerry · Kerry County Council · Planning ref 17698
Construction of Phase 6C of development, consisting of 25 no two-storey dwellings consisting of 10 no detached units, 12 no semi-detached units and 3 no terraced units, with associated roads and ancillary site services all at Shronedarragh, Barraduff, Killarney, Co. Kerry
Notice identity Works stated Scale Commenced
CN0097585KY BCMS open-data feed
Construction of Phase 6E of development, consisting of 13 no two-storey dwellings consisting of 5 no detached units and 8 no semi-detached units with associated roads and ancillary site services all at Shronedarragh, Barraduff, Killarney, Co. Kerry
13 units · 1,722 m²Builder not named
17 Feb 2023
CN0089818KY BCMS owner-supplied export
Construction of Phase 6C of development, consisting of 25 no two-storey dwellings consisting of 10 no detached units, 12 no semi-detached units and 3 no terraced units, with associated roads and ancillary site services all at Shronedarragh, Barraduff, Killarney, Co. Kerry
25 units · 3,311 m²Builder named
06 Jun 2022
CN0080678KY BCMS open-data feed
Construction of Phase 6B of development, consisting of 27 no two-storey dwellings consisting of 7 no detached units and 20 no. semi-detached units, with associated roads and ancillary site services all at Shronedarragh, Barraduff, Killarney, Co. Kerry
27 units · 3,502 m²Builder not named
03 Sep 2021
CN0071402KY BCMS open-data feed
Construction of Phase 6A of development, consisting of 1 two-storey dwelling consisting of a detached 3 bedroom unit, with associated roads and ancillary site services all at Shronedarragh, Barraduff, Killarney, Co. Kerry
1 unit · 140 m²Builder not named
21 Dec 2020
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
17 Feb 2023 · Latest notice
5 notices · phased
Cork, Cork · Cork City Council · Planning ref 16/07292
Construction of 10 no. new dwelling houses, 1 no. apartment/duplex building and associated site works, Nos.16 A to C inclusive Newton avenue, 1-10 inclusive newton square, Newton heights, boherboy road, mayfield, lotamore, cork.
Notice identity Works stated Scale Commenced
CN0099994CY BCMS owner-supplied export
Construction of 10 no. new dwelling houses, 1 no. apartment/duplex building and associated site works, Nos.16 A to C inclusive Newton avenue, 1-10 inclusive newton square, Newton heights, boherboy road, mayfield, lotamore, cork.
37 units · 1,202 m²Builder named
17 Feb 2023
CN0095932CY BCMS open-data feed
Construction 11 no new apartment units, 1 no dwelling house, and associated site works, nos. 5A 5B 6A 6B newton place; nos. 17A to 17D, 18A to 18C all inclusive newton avenue; no. 13 newton place, newton heights, boherboy road, mayfield, lotamore, cork.
12 units · 925.8 m²Builder not named
30 Nov 2022
CN0081810CY BCMS owner-supplied export
Construction of 15 no dwelling houses, including nos. 1 to 5 inclusive Newton Green, nos. 8 to 15 inclusive Newton Green, nos. 18, 19 Newton Green, Newton Heights, Boherboy road, Mayfield, Lotamore, Cork.
37 units · 1,542.6 m²Builder named
01 Oct 2021
CN0077413CY BCMS owner-supplied export
Construction of 8 no. new apartment dewellings in 3 blocks including associated site works, 20A, 20B, 21A, 21B Newton Close, and 21A to 21D (inclusive) Newton Avenue, Newton Heights, Boherboy road, Mayfield, Lotamore, Cork.
37 units · 602 m²Builder named
10 Jun 2021
CN0075180CY BCMS open-data feed
Construction of 22 units and associated site works, 1-19 Newton Close (inclusive), Newton Heights, and 22-24 Newton Close (inclusive), Newton Heights, Boherboy road, Mayfield, Lotamore, Cork.
22 units · 2,265.6 m²Builder not named
26 Apr 2021
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
15 Feb 2023 · Commenced
1 notice · 1 source identity
Dublin, Dublin · Fingal County Council · Planning ref F/313/21
Construction of 31 no. single storey sheltered housing units & single-storey communal facility at Kilhedge lane, Lusk, Co. Dublin.
New build
07 Feb 2023 · Commenced
1 notice · 1 source identity
Mallow, Cork · Cork County Council · Planning ref 15/6119,PL0.246853,20/6130, 22/4819
Proposed Construction of 73 No. Residential Units (1 - 73) and Associated Site Works at Annabella Gate, Rose Hill, Annabella, Mallow, Co.Cork.
New build
26 Jan 2023 · Latest notice
7 notices · phased
Cobh, Cork · Cork County Council · Planning ref 21/05603
Cobh Housing Development - Construction of 38no. 3 bed units, 12no. 2 bed units, 6no. 1 bed units (No's 1-38) and all ancillary site works.
Notice identity Works stated Scale Commenced
SN0008041CC BCMS open-data feed
Block C1 - D2 (Units 1 -4) of Cobh Housing Development. Which is the construction of 38no. 3 bed units 12no. 2 bed units, 6no. 1 bed units (No's 1-38) and all ancillary site works
12 units · 384 m²Builder not named
26 Jan 2023
SN0008043CC BCMS open-data feed
Block C1 - D2 Units 53 - 56 of of Cobh Housing Development. Which is the construction of 38no. 3 bed units 12no. 2 bed units, 6no. 1 bed units (No's 1-38) and all ancillary site works.
12 units · 384 m²Builder not named
26 Jan 2023
SN0008045CC BCMS open-data feed
Block E1 – F2 (Units 44-47) Cobh Housing Development - Construction of 38no. 3 bed units, 12no. 2 bed units, 6no. 1 bed units (No's 1-38) and all ancillary site works.
12 units · 317 m²Builder not named
26 Jan 2023
SN0008046CC BCMS open-data feed
Block E1(M) – F2(M) (Units 26-29) - of Cobh Housing Development. Which is the construction of 38no. 3 bed units 12no. 2 bed units, 6no. 1 bed units (No's 1-38) and all ancillary site works.
12 units · 317 m²Builder not named
23 Jan 2023
SN0008042CC BCMS open-data feed
Block C1(M) D2(M) Units 17 - 20 of Cobh Housing Development. Which is the construction of 38no. 3 bed units 12no. 2 bed units, 6no. 1 bed units (No's 1-38) and all ancillary site works.
12 units · 384 m²Builder not named
20 Jan 2023
SN0008044CC BCMS open-data feed
Block G-H (Units 40-43) - Cobh Housing Development - Construction of 38no. 3 bed units, 12no. 2 bed units, 6no. 1 bed units (No's 1-38) and all ancillary site works.
12 units · 245 m²Builder not named
20 Jan 2023
CN0087309CC BCMS owner-supplied export
Cobh Housing Development - Construction of 38no. 3 bed units, 12no. 2 bed units, 6no. 1 bed units (No's 1-38) and all ancillary site works.
112 units · 4,965.7 m²Builder named
21 Mar 2022
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
03 Jan 2023 · Commenced
1 notice · 1 source identity
Dublin, Dublin · Dublin City Council · Planning ref 2934/21, ABP 312/113-21
Commencement notice for the demolition of extg buildings only, at 63-67 Collins ave east Killester, Dublin 5. Construction of 67 no. new apartment units and 1 no. retail unit will be submitted in a future application.
New build
03 Jan 2023 · Latest notice
5 notices · phased
Straffan, Kildare · Kildare County Council · Planning ref ABP-308003-20
The construction of 30 No. dwellings at Nos. 32-61 incl. An Lumann, New Road, Glebe, Straffan, Co. Kildare
Notice identity Works stated Scale Commenced
CN0096511KE BCMS owner-supplied export
The construction of 30 No. dwellings at Nos. 32-61 incl. An Lumann, New Road, Glebe, Straffan, Co. Kildare
30 units · 3,510.2 m²Builder named
03 Jan 2023
CN0090791KE BCMS owner-supplied export
The construction of 4 No. dwellings at Nos. 62, 63, 64 & 65 An Lumann, New Road, Glebe, Straffan, Co. Kildare.
4 units · 399.6 m²Builder named
29 Jun 2022
SN0007181KE BCMS open-data feed
The construction of 4 no. maisonettes units in 1 block at Nos. 26, 27, 28 & 29 An Lumann, New Road, Glebe, Straffan, Co. Kildare
4 units · 264.3 m²Builder not named
06 May 2022
CN0087089KE BCMS owner-supplied export
The construction of 21 No. dwellings at Nos. 7-25, 30 & 31 An Lumann, New Road, Glebe,Straffan, Co. Kildare.
21 units · 2,536.8 m²Builder named
17 Mar 2022
CN0085974KE BCMS owner-supplied export
The construction of 6 No. dwellings at Nos. 1-6 An Lumann, New Road, Glebe, Straffan, Co. Kildare.
6 units · 648.3 m²Builder named
14 Feb 2022
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
03 Jan 2023 · Latest notice
3 notices · phased
Castletroy, Limerick · Limerick City and County Council · Planning ref 21350
A residential development comprising residential units (65 to 75, 79 to 89), and associated site development works on lands at Newtown Manor Phase 3, Castletroy, Co. Limerick.
Notice identity Works stated Scale Commenced
CN0096825LL BCMS owner-supplied export
The completion of Houses 78 and 90 at Newtown Manor Phase 3, Castletroy, Co. Limerick from 2nd fix of No. 78 and 1st fix of No. 90.
2 units · 210.8 m²Builder named
03 Jan 2023
CN0094484LL BCMS owner-supplied export
Construction of housing units 78 and 90 Newtown Manor, Castletroy, Co. Limerick
Scale not statedBuilder named
13 Oct 2022
CN0087549LL BCMS owner-supplied export
A residential development comprising residential units (65 to 75, 79 to 89), and associated site development works on lands at Newtown Manor Phase 3, Castletroy, Co. Limerick.
22 units · 2,518.4 m²Builder named
25 Mar 2022
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
30 Dec 2022 · Commenced
1 notice · 1 source identity
Kinsealy, Dublin · Fingal County Council · Planning ref F16A/0152/E1A
46 Two storey houses at Abbey Green Baskin Lane, Co. Dublin.
New build
28 Dec 2022 · Latest notice
4 notices · phased
Dublin 1, Dublin · Dublin City Council · Planning ref 4265/18 ABP-305075-19
The proposed development relates to the construction of residential development of between 4 and 7 storeys. The building will contain 47 apartments, a community room with its own entrance, and ancillary facilities.
Notice identity Works stated Scale Commenced
CN0096569DC BCMS owner-supplied export
Construction of single storey residential bike store at Railway St, Dublin 1
75.5 m²Builder named
28 Dec 2022
CN0096573DC BCMS owner-supplied export
Construction of single store bin store for Kiln residents (Bin Store 01) at Railway Street, Dublin 1
28.1 m²Builder named
28 Dec 2022
CN0096575DC BCMS owner-supplied export
Construction of single storey residential bin store (Bin Store 02) at Railway St, Dublin 1
41.3 m²Builder named
28 Dec 2022
CN0094047DC BCMS owner-supplied export
The proposed development relates to the construction of residential development of between 4 and 7 storeys. The building will contain 47 apartments, a community room with its own entrance, and ancillary facilities.
47 units · 4,808.4 m²Builder named
30 Sep 2022
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.