Market / Context

Housing starts: inspect the monthly evidence

Follow each monthly figure to its notice, counting rule and official evidence.

Selected month 2025-12 Closed calendar month
Included phase units 1,857 Source-stated units with explicit holds
Preserved published figure 8,952 Includes scheme figures and older estimates
Source rows 749 647 held or unknown

A commencement notice records an intended start, not completed homes. Phase figures, whole-scheme figures and older estimates remain separate. Limited duplicate-signature checks do not establish national phase deduplication or distinct physical homes.

Source coverage through 2026-09-03. Evidence snapshot 2026-09-05T23:35:49+00:00. A closed calendar month does not establish complete national source coverage.

Month membership uses the validation date, then submitted date, then notified commencement date when the earlier field is absent. This preserves the existing published measure; a notified start can fall in another month.

Retained evidence

Choose a month

current product months and the September 2025 comparison
MonthPublished unitsIncluded phase unitsPeriod
2026-09832831In progress
2026-084,1654,036Closed calendar month
2026-074,1634,085Closed calendar month
2026-064,3383,804Closed calendar month
2026-052,744794Closed calendar month
2026-043,187722Closed calendar month
2026-036,6341,121Closed calendar month
2026-024,9831,098Closed calendar month
2026-015,4241,757Closed calendar month
2025-128,9521,857Closed calendar month
2025-114,914541Closed calendar month
2025-102,969357Closed calendar month
2025-093,240436Closed calendar month

Contribution bridge

2025-12: how the figures relate

zero difference for the stated ledger metric; legacy differences remain explicit
Measure / holdUnits
Source-stated phase units included1,857
Older estimate or unconfirmed scope6,988
Possible repeated phase: same project, start date and units46
Stored official phase evidence could not confirm this value59
No unit quantity stated0
Whole-scheme figure; not counted as another phase2
Current source-row sum8,952
Preserved published figure8,952
Unresolved published/source difference0

Record-level reconciliation

What explains the difference

Calculated from this retained ledger; original figures unchanged

8,952 preserved published units = 1,857 included phase units + 7,095 held source units + 0 unexplained published/source difference.

273 other held rows state no positive source quantity and add zero to this difference. The rule beside each record explains the hold; a whole-scheme hold is not a duplicate finding.

Held noticeMonth basis / notified startUnits heldExact counting ruleEvidence
CN0136589WD2025-12-01 · Validation date
Notified start 2025-12-10
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136587WD2025-12-01 · Validation date
Notified start 2025-12-15
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136555CC2025-12-01 · Validation date
Notified start 2025-12-12
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136553DL2025-12-01 · Validation date
Notified start 2025-12-12
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136583CY2025-12-01 · Validation date
Notified start 2025-12-12
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136573WD2025-12-01 · Validation date
Notified start 2025-12-17
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136563KK2025-12-01 · Validation date
Notified start 2025-12-09
14Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136578KK2025-12-01 · Validation date
Notified start 2025-12-15
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136550CW2025-12-01 · Validation date
Notified start 2025-12-13
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136591TT2025-12-01 · Validation date
Notified start 2025-12-11
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136561WW2025-12-01 · Validation date
Notified start 2025-12-15
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136588WX2025-12-01 · Validation date
Notified start 2025-11-05
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136580FL2025-12-01 · Validation date
Notified start 2025-12-18
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136595GC2025-12-01 · Validation date
Notified start 2025-12-19
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136569WD2025-12-01 · Validation date
Notified start 2025-12-03
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136554CC2025-12-01 · Validation date
Notified start 2025-12-16
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136582CY2025-12-01 · Validation date
Notified start 2025-12-15
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136571KK2025-12-01 · Validation date
Notified start 2025-12-10
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136568CC2025-12-01 · Validation date
Notified start 2025-12-16
1Older estimate or unconfirmed scopeNotice · Official notice fields
CN0136556WW2025-12-01 · Validation date
Notified start 2025-12-01
1Older estimate or unconfirmed scopeNotice · Official notice fields

Inspect all 374 positive-quantity held records

102 included rows connect to 82 verified project identities. 599 rows lack a project destination and 0 lack a public notice page. They remain in the source reconciliation. Locations are not assessed by this ledger.

All source rows · Included phase contributions · Held and unknown

Explore these ledger rows on the map

Download all month rows (CSV) · Month evidence (JSON)

Inspect all preserved monthly figures and evidence availability

Counted values and evidence

2025-12: notices and contributions

50 rows per page; downloads contain all rows
Notice / authorityDatesSeparate source quantitiesCounted unitsRule / holdRecords
CN0136581CY
Cork City Council
2025-12-01
Validation date
Notified start 2025-12-12
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136590WD
Waterford City and County Council
2025-12-01
Validation date
Notified start 2025-10-18
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
SN0013441SD
South Dublin County Council
2025-12-01
Validation date
Notified start 2025-12-05
Phase 207
Scheme 207
207Source-stated phase unitsNotice
Project
Official notice rows
CN0136570WD
Waterford City and County Council
2025-12-01
Validation date
Notified start 2025-12-05
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136557DR
Dun Laoghaire Rathdown County Council
2025-12-01
Validation date
Notified start 2025-12-15
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136584CY
Cork City Council
2025-12-01
Validation date
Notified start 2025-12-15
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136560KE
Kildare County Council
2025-12-01
Validation date
Notified start 2025-12-04
Phase 26
Scheme 4
26Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136572KK
Kilkenny County Council
2025-12-01
Validation date
Notified start 2025-12-11
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136565KK
Kilkenny County Council
2025-12-01
Validation date
Notified start 2025-12-03
Phase 4
Scheme 4
4Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136633OY
Offaly County Council
2025-12-02
Validation date
Notified start 2025-12-15
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
SN0013445GC
Galway County Council
2025-12-02
Validation date
Notified start 2025-12-03
Phase 13
Scheme 13
13Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136626MO
Mayo County Council
2025-12-02
Validation date
Notified start 2025-12-05
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136630KY
Kerry County Council
2025-12-02
Validation date
Notified start 2025-12-12
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136607DC
Dublin City Council
2025-12-02
Validation date
Notified start 2025-12-10
Phase 70
Scheme 1,140
70Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136639GC
Galway County Council
2025-12-02
Validation date
Notified start 2025-12-17
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136611WD
Waterford City and County Council
2025-12-02
Validation date
Notified start 2025-12-17
Phase 24
Scheme 24
24Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136619KE
Kildare County Council
2025-12-02
Validation date
Notified start 2025-12-16
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
SN0013446DC
Dublin City Council
2025-12-02
Validation date
Notified start 2025-12-09
Phase 2
Scheme 2
2Source-stated phase unitsNotice
Project link unresolved
Official notice rows
CN0136669KY
Kerry County Council
2025-12-03
Validation date
Notified start 2025-12-15
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136653MH
Meath County Council
2025-12-03
Validation date
Notified start 2025-12-16
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136704LH
Louth County Council
2025-12-04
Validation date
Notified start 2025-12-17
Phase 9
Scheme 22
9Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136695DL
Donegal County Council
2025-12-04
Validation date
Notified start 2025-12-19
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136682LL
Limerick City and County Council
2025-12-04
Validation date
Notified start 2025-12-22
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project
Official notice rows
CN0136692LS
Laois County Council
2025-12-04
Validation date
Notified start 2025-12-16
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136691LH
Louth County Council
2025-12-04
Validation date
Notified start 2025-12-15
Phase 1
Scheme 4
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136723CC
Cork County Council
2025-12-05
Validation date
Notified start 2025-12-10
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project
Official notice rows
SN0013453GC
Galway County Council
2025-12-05
Validation date
Notified start 2025-12-10
Phase 41
Scheme 56
41Source-stated phase unitsNotice
Project link unresolved
Official notice rows
CN0136731DL
Donegal County Council
2025-12-05
Validation date
Notified start 2025-07-08
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
SN0013455GC
Galway County Council
2025-12-05
Validation date
Notified start 2025-12-10
Phase 41
Scheme 56
41Source-stated phase unitsNotice
Project link unresolved
Official notice rows
SN0013456GC
Galway County Council
2025-12-05
Validation date
Notified start 2025-12-10
Phase 41
Scheme 56
41Source-stated phase unitsNotice
Project link unresolved
Official notice rows
CN0136741WW
Wicklow County Council
2025-12-05
Validation date
Notified start 2025-12-18
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
SN0013454GC
Galway County Council
2025-12-05
Validation date
Notified start 2025-12-10
Phase 41
Scheme 56
41Source-stated phase unitsNotice
Project link unresolved
Official notice rows
SN0013457GC
Galway County Council
2025-12-05
Validation date
Notified start 2025-12-10
Phase 41
Scheme 56
41Source-stated phase unitsNotice
Project link unresolved
Official notice rows
SN0013464CY
Cork City Council
2025-12-08
Validation date
Notified start 2025-12-09
Phase 3
Scheme 3
3Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136764WD
Waterford City and County Council
2025-12-08
Validation date
Notified start 2025-12-19
Phase 44
Scheme 42
44Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
SN0013463CY
Cork City Council
2025-12-08
Validation date
Notified start 2025-12-09
Phase 2
Scheme 2
2Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136758FL
Fingal County Council
2025-12-08
Validation date
Notified start 2025-12-17
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project
Official notice rows
CN0136794WW
Wicklow County Council
2025-12-09
Validation date
Notified start 2025-12-12
Phase 14
Scheme 14
14Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136789WX
Wexford County Council
2025-12-09
Validation date
Notified start 2025-11-24
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project
Official notice rows
CN0136810WD
Waterford City and County Council
2025-12-09
Validation date
Notified start 2026-01-05
Phase 10
Scheme 10
10Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136795WW
Wicklow County Council
2025-12-09
Validation date
Notified start 2025-12-24
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project link unresolved
Official notice rows
CN0136803DR
Dun Laoghaire Rathdown County Council
2025-12-09
Validation date
Notified start 2025-12-23
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136841CY
Cork City Council
2025-12-10
Validation date
Notified start 2025-12-22
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project link unresolved
Official notice rows
SN0013472WH
Westmeath County Council
2025-12-10
Validation date
Notified start 2025-12-08
Phase 4
Scheme 4
4Source-stated phase unitsNotice
Project link unresolved
Official notice rows
CN0136822WH
Westmeath County Council
2025-12-10
Validation date
Notified start 2025-12-18
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
SN0013477MH
Meath County Council
2025-12-10
Validation date
Notified start 2025-12-10
Phase 5
Scheme 5
5Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
SN0013478CC
Cork County Council
2025-12-10
Validation date
Notified start 2025-12-17
Phase 8
Scheme 8
8Source-stated phase unitsNotice
Project link unresolved
Official notice rows
CN0136830KY
Kerry County Council
2025-12-10
Validation date
Notified start 2025-12-19
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136877MO
Mayo County Council
2025-12-11
Validation date
Notified start 2025-12-22
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows
CN0136896WW
Wicklow County Council
2025-12-11
Validation date
Notified start 2026-01-05
Phase 1
Scheme 1
1Source-stated phase unitsNotice
Project page not confirmed
Official notice rows

Page 1 of 3 · 102 rows in this view · Next rows

Official links open an exact, bounded NBCO public notice query. Current external availability is not asserted by this offline build. A missing indexed record or quantity remains an explicit exception.

Use market context as a cue, not proof.

These pages are source-linked context, not demand forecasts, price guidance or proof of live site activity. Turn a useful pattern into alerts, live leads or Premium early access when repeat review matters.